1. gotteeth's Avatar
    Once again...searched everywhere for this. I'm sure the answer was right under my nose, but I cannot find it anywhere.

    When a new task is started, for "status" I have five choices;

    1. Not Started
    2. In progress
    3. Completed
    4. Waiting
    5. Deffered

    Can someone please explain the difference between these choices. "Completed" is obvious but the other four I'm reluctant to assume what they mean.

    Cheers,
    Mike
    12-11-07 12:20 PM
LINK TO POST COPIED TO CLIPBOARD